Excavation and spoil volume calculator
Work out how much material a trench or pit removes in the ground, how much it becomes once it is dug, and how many truck loads that is. Walls can be vertical or sloped, and the swell factor and truck size are adjustable.
Results are for preliminary planning only. They are not a quote, a design or an engineering opinion. The engineer of record, the governing specification and the conditions on site decide what applies to your project.
Use this tool from any AI assistant
Paste this link into ChatGPT, Claude, Gemini, Copilot, Perplexity or any AI assistant and ask it to read the result. The answer carries its source and a link back to this page.
All tools and their parameters are listed at /api/tools/. AI apps that support MCP can connect to https://harrowgategroup.com/mcp.
Formulas used
- Sloped on the long sides only: bank volume = length × depth × (bottom width + slope × depth), where slope is the horizontal run per 1 unit of vertical rise. The same formula covers vertical walls with slope 0.
- Sloped on all four sides: prismoid formula, V = depth ÷ 6 × (A bottom + 4 × A middle + A top). A bottom is length × width, A middle is (length + slope × depth) × (width + slope × depth), A top is (length + 2 × slope × depth) × (width + 2 × slope × depth).
- Loose volume: bank volume × (1 + swell % ÷ 100).
- Truck loads: loose volume ÷ truck body capacity, rounded up to whole loads.
- Conversions: 1 ft = 0.3048 m; 1 m³ = 1.30795 yd³.
Where the defaults come from
- Swell factors. The material presets use the middle of the ranges in the Engineering ToolBox bulk factor table: clay 20 to 40 percent, earth 20 to 30, loam 15 to 25, dry or wet sand and gravel 20 to 30, gravel wet with clay 50 to 60, rock 40 to 80. That is a secondary reference, so treat the numbers as planning values and replace them with your geotechnical figure where you have one.
- Wall slopes. The 1 vertical to 1 horizontal and 1 vertical to 3 horizontal presets are the minimum gradients in section 234(2)(e), (f) and (g) of Ontario Regulation 213/91. Check a specific excavation with our trench shoring requirement checker.
Before you dig
In Ontario, anyone who is going to dig must request locates first, and utility owners mark their buried lines at no charge. Requests go through Ontario Dig Authority, formerly Ontario One Call. Submit the request at least 5 business days before excavation, and request again if the work changes.
Request an excavation quote
A volume gives you a quantity to haul. A quote also reflects soil conditions, groundwater, utilities, access, shoring and the disposal route. Send us the scope and we will arrange a site review and return a written price.
Cite this tool
Copy this HTML to link to the tool from your own page. All of our free planning tools are listed together.
Excavation volume FAQ
What is the difference between bank volume and loose volume?
Bank volume is the volume of material in its natural, undisturbed state in the ground, which is what a pit or trench measures. Once the material is dug it loosens and takes up more space. Loose volume is the bank volume multiplied by one plus the swell factor, and it is the figure that matters for trucking and stockpiles.
How much does excavated soil swell?
The Engineering ToolBox bulk factor table lists a swell of 20 to 40 percent for clay, 20 to 30 percent for earth, dry or wet sand and gravel, 15 to 25 percent for loam, and 40 to 80 percent for broken rock. These are typical published ranges for planning. Use the figure from your geotechnical report where you have one, because swell varies with moisture and how the material is handled.
What slope can an Ontario excavation wall be cut to without support?
Section 234(2) of Ontario Regulation 213/91 sets the minimum gradients. Type 1 and 2 soil must be sloped to 1.2 metres or less from the bottom at one vertical to one horizontal, Type 3 soil at one vertical to one horizontal from the bottom, and Type 4 soil at one vertical to three horizontal from the bottom. The soil type is decided on site under sections 226 and 227.
Does the calculator include compaction or backfill shrinkage?
No. It reports the volume to remove and haul. Compacted backfill is a separate calculation that depends on the fill material, the compaction specification and the volume taken up by pipe, bedding or structure.