Commercial and Industrial Permits in Mississauga, 2018 to 2025

Our analysis of City of Mississauga permit data: 13,101 commercial and industrial permits from 2018 to 2025, by year, type and ward, and what it means.

Commercial and Industrial Permits in Mississauga, 2018 to 2025, commercial construction work by Harrowgate Group in Ontario

Our analysis of City of Mississauga permit data shows 13,101 commercial and industrial permits issued from 2018 to 2025, about 1,600 a year, and nearly half were alterations to buildings that already stand. New buildings were rare: 264 in eight years.

By Harrowgate Group
Last updated: November 11, 2026

If you own or manage a commercial or industrial property in Mississauga, the work you are most likely to plan is a change inside or around an existing building, and it is likely to need cutting, coring, demolition or excavation first. We do that work, and the permit sets the order. Our demolition contractor team can walk you through scope and sequence, and our page on demolition contractor services in Mississauga covers local detail.

How many commercial and industrial permits does Mississauga issue each year?

Between 1,473 and 1,913 a year over 2018 to 2025. The count dipped in 2020, recovered to 1,699 in 2023 and stood at 1,560 in 2025, which is 18 per cent below the 2019 peak of 1,913.

Commercial and industrial permits issued in Mississauga by year and type, 2018 to 2025. Source: our analysis of City of Mississauga Open Data building permit data, downloaded November 11, 2026.
Year issuedAll permitsNew buildingsAdditionsAlterations to existing buildingsDemolitions
20181,816324191014
20191,913354490413
20201,473292662520
20211,546452168714
20221,601401575315
20231,699383680229
20241,493273374419
20251,56018327669
Total13,1012642486,191133

The columns do not add up to the total because the rest are signs (2,506 permits) and other scopes such as sprinklers, tents, change of use and revisions (3,759). Additions combine the data’s “addition to existing building” and “addition and alteration” scopes.

Is Mississauga building new commercial and industrial space, or reworking what exists?

Reworking what exists. Alterations to existing buildings were 47 per cent of all commercial and industrial permits (6,191 of 13,101), while new buildings were 2 per cent (264).

New buildings peaked at 45 in 2021 and fell to 18 in 2025, the lowest in the period. Of the 264, 145 were industrial and 119 were commercial. This is a count of permits for one municipality, and the data does not say why the number fell.

For an owner, the practical meaning is that most projects here are fit-ups, tenant changes and repairs inside live buildings. That is where selective demolition, concrete cutting and coring and scanning with GPR concrete scanning come in, because you are opening floors and walls that already contain services and reinforcing.

Where in Mississauga are the permits concentrated?

Ward 5, by a wide margin. It had 4,979 of the 13,101 permits, or 38 per cent, and also the most new buildings with 69 of 264. Ward 8 and Ward 9 followed.

Commercial and industrial permits issued in Mississauga by ward, 2018 to 2025. Source: our analysis of City of Mississauga Open Data building permit data, downloaded November 11, 2026.
WardAll permitsShareNew buildingsAlterationsDemolitions
54,97938.0%692,25734
81,45311.1%537766
91,1859.0%206097
41,0788.2%35816
11,0297.9%1449817
111,0087.7%3944225
All other wards (2, 3, 6, 7, 10)2,36918.1%661,02838

Ward 2 had 38 new buildings and Ward 11 had 39, which makes them the next most active for construction from the ground up, even though their total permit counts are lower. Every permit in the data has a ward, but a ward is a political boundary, not an industrial area, so use the table to see where activity sits and confirm site conditions on your own property.

How common is commercial and industrial demolition?

Uncommon. Across all permit types, 672 demolition permits were issued from 2018 to 2025, and 133 of them, about 20 per cent, were for commercial or industrial files (81 commercial and 52 industrial). Most of the rest were residential.

The yearly count stayed small: 9 to 29. It peaked at 29 in 2023 and was 9 in 2025. Ward 5 had 34 and Ward 11 had 25 of the 133.

Because there are few of them, each one tends to be a real project, with services to disconnect and often hazardous materials to deal with first. For larger buildings, see our pages on commercial demolition and industrial demolition.

What does Mississauga ask for before a commercial demolition?

Three documents plus a site plan. The City of Mississauga’s page on demolishing a non-residential building lists an Applicable Law Form, a Demolition Report and a General Review Demolition Commitment Certificate.

The site plan must show the address, road location, dimensioned property lines and the outline of existing structures. Drawings must be to scale, in metric, and show what is existing and what you propose. The City may ask for more information during review.

Two connected rules matter. First, Mississauga’s Building By-law 0236-2024 says a permit to demolish is not issued until a demolition control permit is issued under Demolition Control By-law 0045-2019, where that applies. The City describes that by-law as covering residential properties, so most commercial demolitions go through the regular process, but confirm your case with the City. Second, a demolition permit is only one approval; our guide to commercial demolition permits in Ontario covers the others, from asbestos and designated substances to utilities and road occupation.

What does Mississauga ask for before excavation?

An erosion and sediment control permit. The City of Mississauga states that you must get an erosion and sediment control permit before any activity that disturbs the land, such as excavation for construction.

The application needs an erosion and sediment control plan, Conservation Authority approval where applicable, and copies of prerequisite approvals such as a tree permit application or confirmation of well decommissioning. The City says land disturbed by construction must be restored to its original or better condition, and that dewatering discharge goes to a City or Region approved sanitary manhole, not to the street. Applications are emailed to env.approvals@mississauga.ca and staff confirm fees and security deposits afterward.

For a site that needs grading or lot clearing before building, our pages on excavation contractor services, site grading and earthworks and lot clearing for development show how we sequence it.

Checklist: what to have ready before you call

  • The property address and whether it is commercial, industrial or mixed use.
  • Whether the work is an alteration, an addition, a demolition or a new building, since the permit scope follows that.
  • Existing drawings, or a note that none exist, so we can plan scanning of slabs and walls.
  • Any known hazardous materials survey for the building.
  • Whether the work disturbs land, which brings in the erosion and sediment control permit and possibly a tree permit.
  • Your target start date and any tenant or shutdown limits.
  • The City's contact line: 311 (the City's Mississauga 311 service).

How we counted

We downloaded the City of Mississauga’s Building Permits data set on November 11, 2026. It held 35,390 rows. We counted each permit number once (one permit number appeared twice, a residential demolition). Complete calendar years 2018 to 2025 only: 2026 is incomplete and was left out, leaving 32,251 permits.

  • Commercial and industrial: permits whose file type is “Commercial” or “Industrial”, 13,101 in the period or 41 per cent of all permits.
  • Year: the year of the issue date.
  • Included: every status, whether the permit is still open, completed or revoked. Of the 1,560 issued in 2025, 461 were still open with inspections pending. Six commercial or industrial permits in the period were revoked.
  • Type: the data’s scope field. Signs and other scopes are in the totals but not shown as columns.
  • Wards: the ward recorded in the data. No addresses, permit numbers or names are used, and the data’s cost field was not used at all.
  • Checks: we computed every figure twice by two separate methods, and the results matched exactly.
  • Limits: the data records permits, not buildings, and does not say why a permit was sought, how long review took, or whether work was completed.

The City of Mississauga makes this data available under its open data Terms of Use.

Next step

If you have a Mississauga commercial or industrial site in mind, start with our demolition contractor page and tell us what the property is. We will tell you what has to happen first. For the same kind of analysis on another city, see our Toronto demolition permit analysis. For a neighbouring city’s winter rules for commercial owners, read our guide to the Brampton snow removal bylaw.

Frequently asked questions

How many commercial and industrial building permits does Mississauga issue each year?

In our analysis of City of Mississauga permit data, the yearly count of commercial and industrial permits ranged from 1,473 in 2020 to 1,913 in 2019 between 2018 and 2025. The most recent full year, 2025, had 1,560. Most are alterations to existing buildings, not new construction.

Do I need a permit to demolish a commercial or industrial building in Mississauga?

Yes. The City of Mississauga asks for an Applicable Law Form, a Demolition Report and a General Review Demolition Commitment Certificate for a non-residential demolition, along with a scaled site plan. Building By-law 0236-2024 also says a demolition permit is not issued until a demolition control permit is issued where that applies.

Do I need a permit before excavating a commercial site in Mississauga?

The City of Mississauga says you must get an erosion and sediment control permit before any activity that disturbs the land, such as excavation for construction. The application goes to the City's environmental approvals staff with an erosion and sediment control plan. Tree removal and Conservation Authority approvals can be separate.

Which part of Mississauga has the most commercial and industrial permits?

Ward 5 had the most by a wide margin: 4,979 of the 13,101 permits, or 38 per cent, over 2018 to 2025. Ward 8 was next with 1,453. Permit counts show where work is happening, but they do not say why.

How long does a Mississauga permit take to issue?

The public data records the issue date, not the review time, so we cannot say. Review time depends on the completeness of your drawings and any other approvals the project needs. Ask the City's building division for current timelines before you set a schedule.

Get a quote for your project

Tell us about the site, the scope, and your timeline. We review it and reply with the next step.

Free, no-obligation quote & on-site assessment

or
Call (416) 629-0721

← All guides

Companies We've Worked With

Trusted by Leading Organizations

Harrowgate Group delivers commercial and heavy-civil construction for developers, contractors, institutions, municipalities, and property groups across Ontario.

Popeyes logo Popeyes
Tim Hortons logo Tim Hortons
Subway logo Subway
University of Toronto logo University of Toronto
Madison Group logo Madison Group
RioCan logo RioCan
Women's College Hospital logo Women's College Hospital
Starbucks logo Starbucks
Mazda logo Mazda
TD Bank logo TD Bank
City of Toronto logo City of Toronto
Brookfield Properties logo Brookfield Properties
Scotiabank logo Scotiabank
KPMG logo KPMG
Deloitte logo Deloitte
Wells Fargo logo Wells Fargo
Bell logo Bell
Popeyes logo Popeyes
Tim Hortons logo Tim Hortons
Subway logo Subway
University of Toronto logo University of Toronto
Madison Group logo Madison Group
RioCan logo RioCan
Women's College Hospital logo Women's College Hospital
Starbucks logo Starbucks
Mazda logo Mazda
TD Bank logo TD Bank
City of Toronto logo City of Toronto
Brookfield Properties logo Brookfield Properties
Scotiabank logo Scotiabank
KPMG logo KPMG
Deloitte logo Deloitte
Wells Fargo logo Wells Fargo
Bell logo Bell
Call 24/7 (416) 629-0721 Get a Quote