Demolition Permits Issued in Toronto, 2017 to 2025
Our analysis of City of Toronto permit data: 9,780 demolition permits issued from 2017 to 2025, how the count fell, and what it means for your project.
Our analysis of City of Toronto building permit data shows 9,780 demolition permits issued from 2017 to 2025. The yearly count fell from 1,288 in 2017 to 946 in 2025. About four in five were for detached houses, and that share dropped to 72 per cent in 2025.
By Harrowgate Group
Last updated: October 31, 2026
Demolition permits are an early signal of where Toronto is redeveloping, and they set the schedule for everything that follows: utility disconnects, hazardous material removal, excavation and new foundations. We counted them so owners and developers can see what is normal before they plan a project. If you are planning one, our demolition contractor team can walk through scope and sequence with you, and our commercial demolition page covers larger buildings.
How many demolition permits does Toronto issue each year?
Between 907 and 1,318 a year over 2017 to 2025, with a clear drop since 2018. Here is the full table, with detached houses separated from every other building type.
| Year issued | All demolition permits | Detached houses | All other buildings | Detached share |
|---|---|---|---|---|
| 2017 | 1,288 | 1,043 | 245 | 81.0% |
| 2018 | 1,318 | 1,115 | 203 | 84.6% |
| 2019 | 1,102 | 920 | 182 | 83.5% |
| 2020 | 941 | 739 | 202 | 78.5% |
| 2021 | 1,134 | 904 | 230 | 79.7% |
| 2022 | 1,116 | 911 | 205 | 81.6% |
| 2023 | 1,028 | 819 | 209 | 79.7% |
| 2024 | 907 | 723 | 184 | 79.7% |
| 2025 | 946 | 681 | 265 | 72.0% |
| Total | 9,780 | 7,855 | 1,925 | 80.3% |
The three years 2017 to 2019 had 3,708 permits. The three years 2023 to 2025 had 2,881, which is 22 per cent fewer.
Are most Toronto demolitions detached houses?
Yes. Detached houses account for 7,855 of the 9,780 permits, or 80 per cent. Semi-detached houses are next with 290, followed by multiple use and non-residential buildings with 251 and the “other” category with 156.
The more interesting result is the change in 2025. Detached house permits fell to 681, the lowest in the period, while permits for all other buildings rose to 265, also the highest in the period. Across 2017 to 2024 the other-building count stayed between 182 and 245. This is a one-year movement, so we would not call it a trend yet, and the data does not say why it happened.
For owners of commercial and multi-unit properties, the point is that your type of project is not what is shrinking. Industrial, office and mixed-use demolition continues at a steady rate, and those jobs carry different risks from a house. Industrial sites in particular often need hazardous material and equipment decommissioning work first, which we cover under industrial demolition.
Which months have the most permits?
Spring to fall. Pooling all nine years by the month the permit was issued, July (975), October (969), May (957) and September (920) lead, while December (524) and February (606) are the quietest.
To have a permit in hand before the busy months, applying in winter is a reasonable plan. Treat this as a pattern in permit issuance. It does not predict how long a review will take, which depends on the application.
Where in Toronto are the permits concentrated?
Our analysis grouped permits by the first three characters of the property’s postal code. The five busiest areas are listed below. Another 114 permits had no postal code in the data and are left out of this table.
| Postal area (first three characters) | Permits issued | Share of all permits |
|---|---|---|
| M2N | 583 | 6.0% |
| M5M | 392 | 4.0% |
| M3H | 297 | 3.0% |
| M9B | 283 | 2.9% |
| M2M | 280 | 2.9% |
The first area alone has about 6 per cent of all permits in the period, and the top five together have about 19 per cent. Demolition is spread across the city, but it clusters where older detached housing is being replaced.
What does Toronto require before a demolition permit is issued?
Toronto’s Municipal Code, Chapter 363, Building Construction and Demolition, designates the entire city as an area of demolition control. Section 363-6.3 sets different paths depending on the size and location of the residential property. We read the March 2024 consolidation, so check the City’s current text before relying on it.
| Property | What the code says |
|---|---|
| Fewer than six dwelling units, building permit already issued for the new building, former City of Toronto | Notice posted on the property for at least 14 days. If no objection or referral request arrives, the Chief Building Official issues the permit, with a condition that the new building be substantially complete within two years of demolition starting |
| Fewer than six dwelling units, building permit already issued, outside the former City of Toronto | Permit issued with the same two-year completion condition. No posted notice step is set out in this part of the code |
| Fewer than six units with no building permit yet, or six or more units | The Chief Building Official and Chief Planner report to community council, which decides whether to issue or refuse the permit and on what conditions |
In plain terms, a replacement building permit speeds things up for a small residential property, and a larger building or a lot with no replacement plan goes through a council decision. Rental buildings can also trigger a separate review under Chapter 667, which the Chief Building Official assesses first.
Commercial and industrial buildings follow other requirements, including engineering and hazardous material information. We cover those in what a commercial demolition permit requires in Ontario.
What does this mean for your project?
Plan the demolition around the replacement, not the other way round. A few practical points follow from the data and the code:
- Expect a competitive calendar. Permits cluster from spring to fall, and the same contractors, utility crews and inspectors are in demand then.
- Line up the new permit early. For small residential sites, a building permit for the new building is what keeps you on the shorter path.
- Survey for hazardous materials before you finalize scope. Asbestos and other designated substances (see our guide to asbestos abatement in Toronto) change method, cost drivers and schedule.
- Treat utilities as a work item. Water, sewer, gas and electrical disconnects have to be confirmed, not assumed.
- Plan what comes next. Most demolition leads straight into site work, so coordinate with excavation so the site is not left open.
- Decide whether it is a full or a partial demolition. If the building stays occupied or partly stays, selective demolition has different controls for dust, noise and phasing.
Before you call us, have the address, the building type and approximate size, any survey or drawings you hold, and the target start date. We can then tell you what the scope needs and what to ask the City.
How we counted
We used two City of Toronto Open Data sets: Building Permits, Active Permits and Building Permits, Cleared Permits. We downloaded both on October 31, 2026 and combined them.
- What counts: records where the type of work is “Demolition”, counted once per permit number, using the lowest revision on file.
- Year: the year of the issued date. We kept only full calendar years, 2017 to 2025. Permits issued in 2026 are left out because the year is incomplete.
- Excluded: permits with no issued date, and permits with the status “Cancelled”. In the period, 351 cancelled permits were excluded.
- Detached houses: records with the structure type “SFD - Detached”. Everything else is grouped as other buildings.
- Postal areas: the first three characters of the postal code. Permits without a postal code are not in that table.
- Checks: we computed every figure twice by two separate methods, and the results matched exactly.
- Limits: the data records permits, not buildings, so a site with more than one permit can appear more than once. It does not say why a permit was sought or whether the work was done.
Contains information licensed under the Open Government Licence (Toronto).
Next step
If you are weighing a demolition on a Toronto site, start with our demolition contractor page and tell us what the property is. If your site is in Peel, see our Mississauga commercial and industrial permit analysis.
Frequently asked questions
How many demolition permits does Toronto issue in a year?
In our analysis of City of Toronto permit data, the yearly count ranged from 907 in 2024 to 1,318 in 2018 between 2017 and 2025. The most recent full year, 2025, had 946. Counts depend on how many sites are redeveloped, so they move with the housing and construction cycle.
Do you need a demolition permit for a house in Toronto?
Yes. Toronto's Municipal Code Chapter 363 designates the whole city as an area of demolition control, and demolishing a residential property goes through a demolition permit process. Rules differ by size and location, so confirm your case with Toronto Building before any work starts.
Why did detached house demolitions fall in 2025?
The data shows the fall but not the cause. In 2025 detached houses made up 72 per cent of demolition permits issued, down from 80 per cent over the whole period. Higher borrowing costs, slower redevelopment and changes in how projects are approved are all possible factors, but this data cannot separate them.
Does a demolition permit cover asbestos and hazardous materials?
The permit and the hazardous material work are separate. A permit allows the demolition, while asbestos, lead and other designated substances are handled under their own worker safety and environmental rules. Have the building surveyed before demolition is planned, so the findings can shape the scope and schedule.
What is the difference between a demolition permit and a building permit?
A demolition permit allows the existing building to be taken down. A building permit allows the new one to be built. For small residential properties in Toronto, the order of the two matters, because the code ties the demolition permit to a building permit for the replacement.